Project Charter Templates and Examples for Small Business

Project charter templates and two filled examples for small business: the sections to include, how long it runs, and how it differs from a project plan.

EntraWorld Team

·

October 15, 2026

·

6 min read

A small architectural model of a building on a wooden desk by a tall window overlooking a dusk skyline

A project charter is a short document that says what a project is for, what it will deliver, who is involved, and who has approved it, all before real time or money goes in. Good project charter templates give you that structure on a page or two. For a website launch, a new service line, or an event, a charter is how you agree on the finish line before you start running.

Big organizations use charters to authorize large programs. Founders can use the same tool at a smaller scale, and it pays off quickly: a one-page charter settles questions about scope, budget, and ownership while they are still cheap to settle.

What a project charter is (and what it is not)

Asana describes a project charter as a concise, formal document that officially authorizes a project and secures approval before work begins. Its list of core elements is a good checklist: purpose and objectives, scope, success criteria, key stakeholders and roles, a high-level timeline with milestones, a budget estimate, and risks and assumptions.

A charter is not the project plan. The plan comes after approval and carries the detail: task lists, dates, owners, and communication routines. Asana's framing is that a project plan builds on the charter. Think of the charter as the "should we do this, and what does done look like" document, and the plan as "how exactly will we do it."

Length matters too. ClickUp's guide to project charters puts a typical charter at two to four pages and quotes the PMBOK Guide's third edition, which describes it as the document that formally authorizes the project. For a small business, one page is often enough. If yours runs longer, you are probably writing the plan.

Who writes it when the team is you

ProjectManager's charter guide notes that a project manager typically writes the charter, with the sponsor, key stakeholders, and team members involved. In a small venture, you may be the sponsor, the manager, and the entire team at once.

The charter still earns its place. Writing down the objective and the scope forces decisions you would otherwise make halfway through the work, under pressure. If you work with a partner, a contractor, or a client, it also gives everyone one document to point to when someone asks, "Wait, was that included?"

If a client or funder needs to approve the work before it begins, you may also need a project proposal. The proposal asks for a yes. The charter records what the yes covered.

Project charter templates: the sections to include

Use the table below as your template. Each row is a section, with a prompt for what to write.

SectionWhat to write
Project nameA short, specific label
PurposeOne or two sentences on why this project exists
ObjectivesTwo to four outcomes you can check, with numbers and dates
Scope: inWhat the project will deliver
Scope: outWhat it will not deliver (be explicit)
Success criteriaHow you will know it worked
Stakeholders and rolesWho decides, who does the work, who needs updates
TimelineStart date, end date, and three to five milestones
Budget estimateCash cost and hours, with a margin for surprises
Risks and assumptionsThe top three things that could change the plan
ApprovalNames, roles, and the date each person signed off

The "scope: out" row is the one most people skip, and it is the one that prevents the most arguments. M State's page on project charters adds another reason to keep the document: a charter can be referenced throughout a project's lifecycle to judge how well the work went and to improve future projects.

EntraWorld's AI business plan generator can produce a first draft of your goals, milestones, and budget assumptions. Pull the pieces that apply to this project into the objectives and timeline rows, then edit them to match the specific work.

Example 1: launching a service website

Here is how the template reads when it is filled in for a small design studio building a new website. The details are invented for illustration.

  • Purpose: Replace the current one-page site with a multi-page site that explains each service and takes inquiries.
  • Objectives: Launch by November 30. Reach 20 inquiry form submissions in the first two months.
  • Scope in: Five pages (home, services, portfolio, about, contact), an inquiry form, basic search setup.
  • Scope out: A blog, online payments, and any content in a second language.
  • Success criteria: Site live on the main domain, inquiry form tested end to end, owner approves final copy.
  • Stakeholders: Owner (decides), freelance developer (builds), copywriter (writes), two past clients (review).
  • Timeline: Copy due October 25, design approved November 5, build complete November 20, launch November 30.
  • Budget estimate: Developer and copywriter fees plus 15% margin; owner time of about 20 hours.
  • Risks: Copy arrives late, developer availability, form notifications landing in spam.

Example 2: adding a new service line

A service business adding a second offer can use the same structure with different content.

  • Purpose: Test whether existing customers will buy a monthly maintenance plan alongside one-time projects.
  • Objectives: Sign 10 plan customers by the end of the first quarter. Keep the plan profitable at the planned price.
  • Scope in: Plan terms, pricing page, an email to current customers, a simple scheduling process.
  • Scope out: New hires, new software, and any marketing to people who are not already customers.
  • Success criteria: Ten signed customers, each plan covered by the hours budgeted.
  • Stakeholders: Owner (decides and sells), operations lead (schedules the work).
  • Timeline: Terms drafted in two weeks, email sent in week three, first review at day 60.
  • Budget estimate: Mostly owner time; small cost for contract and page updates.
  • Risks: Customers want custom terms, workload spikes crowd out plan visits, price is set too low.

If you need contract language for plan terms, EntraWorld's legal forms and contract templates give you a starting point, so the paperwork does not become the thing that holds the launch up.

How to get a charter approved and used

A charter is only useful if people read it and agree to it. A few habits help:

  1. Draft it in one sitting. Aim for 60 to 90 minutes. If it takes longer, the project may not be defined clearly enough yet.
  2. Share it before the kickoff. Ask each stakeholder one question: "What is missing or wrong?"
  3. Get a visible yes. An email reply or a signature works. What matters is that approval is written down.
  4. Set a change rule. Decide now how scope changes get approved, such as a short email to the sponsor with the cost and date impact.
  5. Revisit it at each milestone. Reread the objectives and success criteria and ask whether the work still matches them.

From charter to plan

Once the charter is approved, the detail goes into your plan. Our project plan template picks up where the charter ends, and the business action plan template shows how to turn objectives into weekly tasks. For a longer horizon, the 90-day small business planner helps you stack several projects without overloading yourself.

Draft your charter this week

You can write a useful charter in an hour. Pick the next project that matters, fill in the table above, and send it to whoever has a stake in the result. You will likely find a missing assumption or an unclear boundary before it costs you anything.

A charter works best as one stage in a larger path from idea to launch. Explore EntraPath, the guided founder roadmap that breaks the path from idea to launch into phases, and write a one-page charter for each major step along the way.